Should you bid at this price?

Type the estimate and the percentage you are thinking of quoting to see what actually reaches your bank, and the percentage below which you start losing money. Bidding for manpower on GeM? Switch to Manpower on GeM below.

The tender
Type a minus figure if you are quoting above the estimate.
Replace this the moment you have your own rate analysis.
Sand, murum or stone on this job? Type the assessed royalty, but only if your cost percentage above leaves it out.
Contract termshow long, what is guaranteed, what you borrow
2.5% is the usual condition — check your agreement.
12 if you leave it blank.
12 — check your agreement.
5% — CPWD's condition, not a statute. Your NIT's schedule says what it is a percentage of.
1.5% a year is typical; your bank may differ.
The guarantee is on
Whichever is higher — what most 2026 CPWD-pattern NITs say. Below the estimate that means the guarantee is on the estimate.
The guarantee runs to completion plus 60 days, so we price the commission for 14 months. The security deposit, not the guarantee, covers the defect liability period.
CPWD and many central works since 27 Feb 2026 — check your NIT. Below 80%, you give the department the gap as a further guarantee.
0 — most small contracts offer no advance.
10% — CPWD clause 10B.
Recovery starts once 10% of the work is paid and finishes at 80%, so on average the advance is outstanding for about the first 45% of the work — that is what we charge interest on.
Nil by default — small enterprises and recognised startups are exempt, and many tenders take a bid-securing declaration instead.
5 — what divisions usually withhold; 1 is the assessment itself. At 5× it is usually the largest locked item on the page.
6.
Deductions the department makesthe rates and what they are taken on
18% on all works contracts since 22 September 2025.
1% is the notified rate.
Cess is taken on…
The department deducts cess as an advance on the bill; the final cess is assessed on the cost of construction, and a 2026 Kerala High Court ruling says separately supplied items need not be in it. Divisions deduct on both bases, so we show you the difference.
Deducted where the contract is more than ₹2,50,000, on the value before tax. It reaches your cash ledger, not your bank.
2% for a firm or company, 1% for an individual or a HUF.
Income-tax TDS is taken on…
Anything else your division recovers
Your money and the timingyour cost of funds, overheads and when things come back
5%.
11% — a typical working-capital limit.
1.
2.
12.
Switch it off for the marginal number — the point below which this job stops paying for itself, ignoring the office.
Names on the printed sheetthe work, the tender number and your letterhead
Printed on your working paper exactly as typed; left blank, the line is left off.
Used as the heading when no firm letterhead is entered.
Firm letterhead — remembered on this device
Your answer

    From the estimate down to your bank
    What it costs you outside the bill
    What you make is the contract value less this total.
    Want a CA to look at this before you quote? Karan does these — the deduction stack, the agreement and the cash plan together. The Excel takes an afternoon; this took two minutes.

    Not sure you qualify to bid at all? Work out your bid capacity first.

    Won the work and the bill came short? Rebuild the deductions on one RA bill.

    How this worksthe method, the assumptions and the sources

    The method. We take the estimate, apply your quote to get the contract value, and take off every deduction the department makes from the bill. What is merely held back is financed at your cost of funds instead of being treated as lost.

    One reading is contested. Labour cess is charged on the cost of construction, and the better view is that GST is not part of that cost — but no circular decides it, and divisions deduct on both bases. The other side of it is that a cess charged separately would itself go into the GST value.

    What is deducted is provisional — section 100(4) makes it subject to final assessment, and any excess comes back on assessment (D. Manoharan v. Union of India, Kerala High Court, 19 August 2026).

    What this page leaves alone. The Supreme Court's mineral-levy decisions and the mining amendment of 2026 concern state levies on mineral rights, not GST, and the law is unsettled — nothing here is computed from them. It also says nothing about what you should quote; that is a commercial judgment with competitors in it.

    What is contested, and what is yours to check. Three of the figures are assumptions, not law, and are marked: your cost as a percentage of the estimate, your cost of funds and your bank’s guarantee commission. One reading is contested and is marked: whether GST forms part of the cost of construction for labour cess. The security deposit, performance guarantee and any mobilisation advance are your contract’s terms — check the agreement, not this page. This is a working paper for your own file, not an opinion, and it does not tell you what to quote.

    • Works contracts at 18% GST — Notifications 11–17/2025-CT(R) dated 17.09.2025, effective 22.09.2025.
    • GST TDS at 2% above ₹2,50,000 on the value excluding tax — section 51 of the CGST Act.
    • Income-tax TDS on contracts — section 393(1) Table Sl. No. 6(i) of the Income-tax Act, 2025 (2% for a firm or company, 1% for an individual or HUF).
    • Labour cess at 1% of the cost of construction — section 100 of the Code on Social Security, 2020, at the rate notified by S.O. 2322(E) dated 8 May 2026, which superseded S.O. 2899 of 26 September 1996. The Cess Act, 1996 was repealed by section 164(1) of the Code when the labour codes came into force on 21 November 2025; the rate is unchanged, and the levy was upheld on the earlier Act in Dewan Chand Builders & Contractors (Supreme Court, 18 November 2011).
    • Bid security and performance security — Rules 170 and 171 of the General Financial Rules, 2017; the 5% performance guarantee plus 2.5% security deposit split is CPWD's condition, not a statute.
    • Mobilisation advance up to 10% at 10% simple interest — CPWD clause 10B.